Search

Quality Engineering and Construction

All about quality in building construction industry

Category

Method Statement

Detailed steps in carrying out an activity

Floor screeding works (substrate for marble tiled floor)

This is a comprehensive and photographic method statement of floor screeding works. Screed can be final finish or a substrate of the final floor finishes like homogenous tiles, marble floor or granite floors. This step by step method can be useful for all newbies who would like to learn floor screeding.

The step by step method is listed below:

20150117_090521

Create level pegs on the floor to be screed. This will serve as a guide when leveling the wet screed.

20150117_085042

When the level pegs are dry, clean the floor by using water jet and sweep away the excess water.

20150117_094437

Before screeding starts, ensure that the floor to receive the screed is very clean.

20150117_085059

Prepare the cement mixer and bucket for screed powder mixing.

20150117_085743

Place the screed premix powder to the cement mixer.

20150117_090012

Add water to the mixer on to the amount recommended by the screed powder manufacturer.

20150117_090040

While mixing the screed, prepare and mix bonding agent and OPC.

20150117_090120

Use hand held electric mixer and mix until flowable consistency.

20150117_090604

Pour and spread out the bonding layer over the floor area to be screed.

20150117_090741

The bonding layer must be evenly spread to ensure that all screed will bond to the concrete surface.

20150117_091015

Bring the screed mix unto the floor area until the desired quantity is achieved.

20150117_091113

The screeding must start immediately before the bonding layer lost its tuckiness.

20150117_091241

Use a long straight trowel and begin leveling the screed to desired thickness pressing onto the level pegs.

20150117_091405

Work from sides to sides pressing the screed to compact it.

20150117_091823

Move to the other side and repeat the step above.

20150117_093418

Now move backwards and level the screed in a diagonal position. Always stamp and press the screed for better compaction.

20150117_092348

If the screed thickness is not enough, top up using a trowel and level it. Repeat the steps above until the entire floor is covered with screed.

20150117_092336

The screeding should end at the door area or at the free end where foot or traffic is allowed. Allow the screed to harden and cure for 7 days.

20150117_095102

The finished screed for marble floor substrate should be rough and not trowelled to smooth surface. This is for good bonding between the tile adhesive and the substrate. Before tiling work starts, a good practice to avoid abortive costs is to check for debonding of screed or commonly known as hollowness. If there are any hollowness found, repair is a must to eliminate the problem after tiling works.

The repair of hollowness will be the topic on my next post.

 

 

 

Advertisements

Method Statement of Slab Construction (Cast-In Situ)

Quality Engineering and Construction

This method is meant to help the new graduates understand how to construct a cast-in situ slab. I try to minimize the words and fill many photographic images in sequence as pictures could expound better than words. So here we go.

Erect the slab formwork either using conventional scaffold framing and timber combination or using system formworks.
slab 1
After the slab formwork is done, apply releasing agent using rollers for ease of striking. Meanwhile, the slab reinforcement bars can be brought into the slab formwork ready for installation.
slab 2
Lay the main reinforcement bars of bottom layer of the slab spaced evenly according to design or drawings.
slab 3
Tie the reinforcement bars at both ends to maintain the spacing.
slab 4
Lay the distribution bars and tie them to the main reinforcement bars.
slab 5
Install additional slab reinforcements if there’s any.
slab 6
After completing the bottom layer of slab reinforcement, allow the M&E contractors to lay the concealed…

View original post 405 more words

Method Statement of Structural Crack Repair Using Epoxy Resin (Pressure Injection)

This is a detailed sequence on how to carry out pressure injection of Epoxy resin to slab soffit cracks using electric pump. All the materials used and procedure are strictly in compliance to manufacturer’s recommendation. Please note that this is not an advertisement of the product featured below. You can use other products such as Tamseal etc.

Material used in this crack repair:

crack 13 Epoxy Resin

crack 14Putty

Demonstration Process:

1. Locate the crack and drill 13mm dia holes along the crack at 300mm interval.

crack 1

2. Insert the nipples to the drilled holes and tighten it to prevent from pull-off action when the pressure gets higher.

crack 2

3. Apply Estorex Putty from end to end of the crack line by using trowel or spatula. Wait for the putty to dry in about 5hrs.

crack 3

4. The crack line must be sealed with Estorex Putty to prevent the epoxy grout from oozing during pressure injection. Ensure that the crack line is dry before starting any epoxy injection.

crack 4

5. Fill in Part A (Estofill Base) compound to the funnel of the electric pump. The mixing ratio by weight is 3 parts of Estofill Base and 1 part of Estofill Hardener.

crack 5

6. And then fill-in Part B compound (Estofill Hardener). Mix thoroughly until a uniform mixture is achieved.

crack 6

7. Install the injection tube to the nipple.

crack 7

8. Once ready, start pumping the epoxy grout to the injection nipples until the pressure goes up. Pumping may take up to 5 minutes to fill-in depending on the extent and depth of the crack

crack 8

9. Observe and control the pressure not to reach higher than 10bars.

crack 9

10. While pumping the epoxy resin into the cracks, the pump will not show any increase in pressure. Only when the cracks are filled up will the pressure start to rise. If the cracks are small, the pressure can rise very fast in some instances hence it is quite difficult to control.

crack 10

11. Transfer the injection hose to the next nipple and repeat steps from 8 to 10.

crack 11

12. A good practice is to clean the electric pump and injection hose by using thinner. This is always done before the first pumping and after using before the break period. It is mainly to remove any compound left in the pump and prevent blockage.

crack 12

Method Statement of Column Construction (cast-in king-post of temporary deck/bridge)

In some cases, temporary structures are deemed permanent when its location and purpose coincides with the master plan. Design have to be modified in order to cater the influence of such temporary structure. Most of them are king posts supporting temporary deck for crane or pump car parking. RC columns reinforcements should be changed to smaller sizes when the steel area and inertia of the steel king-post is considered. This is on the design change part but on this article, I will show you the actual construction of RC column with cast-in king-post. I will go through some of the steps and some tips on how to get a good finished concrete quality of RC column. As usual I will show some actual photos to help the readers understand the important steps and procedures.

column 3

For good bonding between steel column and concrete, wash thoroughly using high pressured water jet to remove dusts and oil.

column 4

Ensure that the base construction joint is roughened and clean before closing of formwork.

column 5

Close the formwork once the rebars are inspected and cleanliness is accepted by the client representative.

column 6

To prevent bulging surface and column deformation due to concrete pressure, install walers at maximum of 600mm distributed along the column height.

column 7

Check the column formwork verticality and braces should be enough to prevent from swaying during concrete placement. Gaps must be sealed to prevent grout loss. Remember that the aim is to have a good finished concrete quality. Concrete workers handling the vibration pokers must be trained on how to compact wet concrete for vertical elements. Pouring shall be done in layers of 1m and vibration draw-out at 1m per second. Too much vibration will lead to segregation and less vibration may cause honeycomb. Only when no more air bubbles should the compaction would stop.

column 9

When concreting is done, remove the supports, walers and formwork after 24hrs.

column 11

When the formwork is removed, you should notice that a good concrete surface quality is achieved.

At this stage, a post-pour inspection should be carried out by the engineer to record the quality of concrete. A clearance is given when there are no defects recorded like honeycomb, minor grout loss and bulging surface. If such defects are found, it should be rectified and re-inspected before a clearance is given to proceed the next stage of work.

I think that is all that I can share for this topic. Please feel free to comment and share this post if you find it useful.

I hope you enjoyed reading my post.

Thanks,

Rey Joy Mangubat

Method Statement of Slab Construction (Cast-In Situ)

This method is meant to help the new graduates understand how to construct a cast-in situ slab. I try to minimize the words and fill many photographic images in sequence as pictures could expound better than words. So here we go.

Erect the slab formwork either using conventional scaffold framing and timber combination or using system formworks.
slab 1
After the slab formwork is done, apply releasing agent using rollers for ease of striking. Meanwhile, the slab reinforcement bars can be brought into the slab formwork ready for installation.
slab 2
Lay the main reinforcement bars of bottom layer of the slab spaced evenly according to design or drawings.
slab 3
Tie the reinforcement bars at both ends to maintain the spacing.
slab 4
Lay the distribution bars and tie them to the main reinforcement bars.
slab 5
Install additional slab reinforcements if there’s any.
slab 6
After completing the bottom layer of slab reinforcement, allow the M&E contractors to lay the concealed services.
slab 8
Install bar chairs acting as spacers between top and bottom reinforcements.
slab 7
Lay the top reinforcements with distribution bars fixed on first and the main reinforcements on the upper layer (transverse direction).
slab 9
After completing the slab top reinforcements, clean and blow away the dust by using compressed air.
slab 10
Meantime, the surveyor must check the formwork level and install the markings for the concrete level.
slab 11
After the formwork level measurements are done, furnish the copy from the surveyor and locate the area which varies from the correct level.
slab 12
After the adjustment is done, do a routine formwork inspection to check the stability of the frames and runners.
slab 14
Ensure the slab level markers are fixed nice and tight so that it will not move during the concrete pouring operation.
slab 13
Check all the formwork gaps and ensure that they are plugged before concrete placement. Concrete slurry will flow through the gaps and will lead to grout loss if not rectified.
slab 15
Spray water to the formwork and reinforcements to lower down the temperature. Wet concrete temperature must be less than 35deg Celsius during pouring.
slab 16
Prepare the vibrator machine while waiting for the concrete truck to come. It is always good to have a back-up vibrator if in case something goes wrong.
slab 17

All concrete trucks must report to the cube room for slump test. The arrival time will be recorded.

slab 18

Check the slump height whether it is within the tolerance, if not the concrete would be rejected. A note to the D.O. reflecting the slump stating  “REJECTED”.

slab 18.1

Only those trucks that passed the slump test would be allowed to unload the concrete.

slab 17.1

slab 17.2

Meanwhile, make test cube samples for the concrete batch. Normally for slab, cube must be taken at every 50 cu.m. (refer to project specification). Total 3 + 3 cubes shall be made for 7-day and 28-day test, respectively. You can make extra cubes if you want just for the purpose of earlier test like 3-day test or for water absorption test if you are using waterproofing admixture.

slab 19

Proceed to concrete placement and maintain sufficient light when the operation reaches dusk or even until midnight.

slab 20

On the next day, check the concrete slab surface and ensure it is sufficiently dry after 12hrs. If not, no traffic shall be allowed until its hard enough.
slab 21
Spray water and flood the concrete to cure and repeat when it’s needed.

slab 22

Please feel free to comment and share your thoughts to improve the procedures above.

Thanks,

Rey Joy Mangubat

Create a free website or blog at WordPress.com.

Up ↑

%d bloggers like this: